Westerly

CASE STUDY

Working with local emergency managers, researchers found 30 structures deemed critical infrastructure that were at risk of flooding.

Background

In 2016-17, a pilot study was conducted with critical facility managers in Westerly, RI, using semi-structured interviews and participatory mapping. Interview methods were based on existing practices for vulnerability assessments, and further augmented to obtain compatible data for use with hurricane modeling outputs. Westerly is a coastal community on Rhode Island’s southern coast with a population of about 18,000 as of 2010. Westerly was chosen as the pilot community because of its relatively small number of critical facilities and high level of hazard exposure. The combination of hazard exposure and limited number of facilities allowed for investigation of interdependencies between facilities and cascading consequences of particular concern to emergency managers.

Figure 1: Storm impact model for Westerly’s critical facilities showing wind and inundation CTs triggered by hypothetical Hurricane Rhody 30 minutes and two hours after landfall. The red pin in front is a CT triggered by one foot of flooding and represents a fire chief’s concern that, “When it floods above a foot here, we can’t reach the homes around the lighthouse.” Yellow pins show where inundation blocks roads.

Analysis

The Westerly pilot study was carried out in collaboration with the Rhode Island Emergency Management Agency (RIEMA). The collaboration facilitated conversations with local Emergency Managers to identify critical facilities in Westerly, a necessity as infrastructure vulnerability information is generally proprietary and sensitive. A total of 30 critical facilities were identified, including fire departments, police stations, hospitals, and wastewater treatment plants. 13 facility managers from 11 of 30 critical facilities in Westerly were interviewed. This included four fire departments, the police station, the dispatch center, the ambulance corps, the waste water treatment plant, the water department, the largest electrical distribution substation and the department of public works.

An open-ended interview instrument was used to collect a wide range of facility manager storm concerns. Facility managers were asked for their immediate hazard concerns during a storm and were also prompted to consider how storm consequences on other parts of the community (e.g. roads) could affect their facility. Interviewees were asked for the location of their concern(s) and for the perceived threshold(s) (e.g., inundation depth, wind force) which would trigger their concern. A single Consequence Threshold was created for each concern, composed of the location of the asset of concern, the modellable hazard or storm force perceived as a risk to that hazard, the threshold of the storm force which triggers the hazard, and the consequence of that threshold being triggered. This collection method resulted in the identification of 201 Consequence Thresholds (CTs).

Figure 2: Maximum flooding impact from the hypothetical Hurricane Rhody is shown.

Impacts

After the CTs were collected, they were integrated into a high-resolution storm surge model (ADCIRC) coupled with nearshore waves (SWAN) hydrodynamic model. For the Westerly pilot study, a synthetic hurricane based on several historical storms that have impacted the region, called Hurricane Rhody, was developed to simulate the effects of a high-impact storm on the coast. Once the CTs were integrated within the storm model, the parameters of the model (e.g., surge, wind speed, and flooding) triggered concern thresholds upon running the model. Not all of the 201 collected CT could be incorporated into the Westerly storm impact model. Two primary challenges when integrating the CTs with the storm impact data were identifying quantifiable modellable thresholds for each CT (e.g., 1 ft of inundation, 80 mph wind speeds) and unknown locations of concerns. These are of vital importance for integration with the storm impact model as the outputs of the model are water levels, wind speeds, and waves throughout the time series of the storm at each geographic location within a modeled area. As a result of these challenges, only 96 of the 201 collected Consequence Threshold were incorporated into the storm impact model for the Westerly pilot study.

After incorporating the 96 Consequence Thresholds into the storm impact model for Westerly, the results were utilized to develop a hypothetical damage timeline resulting from storm Rhody. As inundation and winds increase during the storm, different CTs throughout Westerly are triggered and the box details the impacts resulting from these triggered CTs and the time during the storm when the CT is triggered.

While the Westerly pilot study only integrated the collected local CTs with one synthetic storm, the hypothetical scenario shows how incorporating qualitative consequences into storm impact models can facilitate storm hazard scenario planning to help communities to prepare for disasters.

Read more at

Background

In 2016-17, a pilot study was conducted with critical facility managers in Westerly, RI, using semi-structured interviews and participatory mapping. Interview methods were based on existing practices for vulnerability assessments, and further augmented to obtain compatible data for use with hurricane modeling outputs. Westerly is a coastal community on Rhode Island’s southern coast with a population of about 18,000 as of 2010. Westerly was chosen as the pilot community because of its relatively small number of critical facilities and high level of hazard exposure. The combination of hazard exposure and limited number of facilities allowed for investigation of interdependencies between facilities and cascading consequences of particular concern to emergency managers.

Figure 1: Storm impact model for Westerly’s critical facilities showing wind and inundation CTs triggered by hypothetical Hurricane Rhody 30 minutes (Panel A) and two hours (Panel B) after Rhody’s landfall. The red pin in front is a CT triggered by one foot of flooding and represents a fire chief’s concern that, “When it floods above a foot here, we can’t reach the homes around the lighthouse.” Yellow pins show where inundation blocks roads.

Analysis

The Westerly pilot study was carried out in collaboration with the Rhode Island Emergency Management Agency (RIEMA). The collaboration facilitated conversations with local Emergency Managers to identify critical facilities in Westerly, a necessity as infrastructure vulnerability information is generally proprietary and sensitive. A total of 30 critical facilities were identified, including fire departments, police stations, hospitals, and wastewater treatment plants. 13 facility managers from 11 of 30 critical facilities in Westerly were interviewed. This included four fire departments, the police station, the dispatch center, the ambulance corps, the waste water treatment plant, the water department, the largest electrical distribution substation and the department of public works.

An open-ended interview instrument was used to collect a wide range of facility manager storm concerns. Facility managers were asked for their immediate hazard concerns during a storm and were also prompted to consider how storm consequences on other parts of the community (e.g. roads) could affect their facility. Interviewees were asked for the location of their concern(s) and for the perceived threshold(s) (e.g., inundation depth, wind force) which would trigger their concern. A single Consequence Threshold was created for each concern, composed of the location of the asset of concern, the modellable hazard or storm force perceived as a risk to that hazard, the threshold of the storm force which triggers the hazard, and the consequence of that threshold being triggered. This collection method resulted in the identification of 201 Consequence Thresholds (CTs).

Figure 2: Maximum flooding impact from the hypothetical Hurricane Rhody is shown.

Impacts

After the CTs were collected, they were integrated into a high-resolution storm surge model (ADCIRC) coupled with nearshore waves (SWAN) hydrodynamic model. For the Westerly pilot study, a synthetic hurricane based on several historical storms that have impacted the region, called Hurricane Rhody, was developed to simulate the effects of a high-impact storm on the coast. Once the CTs were integrated within the storm model, the parameters of the model (e.g., surge, wind speed, and flooding) triggered concern thresholds upon running the model. Not all of the 201 collected CT could be incorporated into the Westerly storm impact model. Two primary challenges when integrating the CTs with the storm impact data were identifying quantifiable modellable thresholds for each CT (e.g., 1 ft of inundation, 80 mph wind speeds) and unknown locations of concerns. These are of vital importance for integration with the storm impact model as the outputs of the model are water levels, wind speeds, and waves throughout the time series of the storm at each geographic location within a modeled area. As a result of these challenges, only 96 of the 201 collected Consequence Threshold were incorporated into the storm impact model for the Westerly pilot study.

After incorporating the 96 Consequence Thresholds into the storm impact model for Westerly, the results were utilized to develop a hypothetical damage timeline resulting from storm Rhody and is shown in Box 1. As inundation and winds increase during the storm, different CTs throughout Westerly are triggered and the box details the impacts resulting from these triggered CTs and the time during the storm when the CT is triggered.

While the Westerly pilot study only integrated the collected local CTs with one synthetic storm, the hypothetical scenario shows how incorporating qualitative consequences into storm impact models can facilitate storm hazard scenario planning to help communities to prepare for disasters.

Read more at

Case Studies

Westerly
case study
Research in Westerly identified more
than 100 "consequence thresholds"
resulting from impacts to 11 critical infrastructure facilities in the floodplain.

Click here to learn more.
Providence
case study
Research in Providence
identified approximately 300
"consequence thresholds"
resulting from impacts to
about 100 assets across
the 45 critical infrastructure facilities
in the floodplain.
Naval Station Newport
on Aquidneck Island
case study
Our latest case study focuses on
"A hazard resilient future for Naval Station Newport within its coastal
Community: Military installation resilience
review for short-term preparedness
and long-term planning."
Wastewater Treatment Facilities
case study
In this case, a customized planning tool was developed to help the Rhode Island Department of Emergency Management (RI DEM) plan for the 19 major wastewater treatment facilities that it regulates.
Westerly
case study
Research in Westerly identified more than 100 "consequence thresholds" resulting
from impacts to
11 critical infrastructure
facilities in the floodplain.
Providence
case study
Research in Providence
identified approximately 300
"consequence thresholds" resulting from
impacts to about
100 assets across
the 45 critical
infrastructure facilities
in the floodplain.
Naval Station Newport
case study
Our latest case study focuses on
"A hazard resilient future for Naval Station Newport
within its coastal
Community: Military installation resilience review for short-term preparedness and long-term planning."
Wastewater Treatment Facilities
case study
In this case, a customized planning tool was developed
to help the Rhode Island Department of Emergency Management (RI DEM) plan
for the 19 major wastewater treatment facilities that it regulates.
Westerly
case study
Research in Westerly identified more than
100 "consequence thresholds"
resulting from impacts to 11 critical
infrastructure facilities in the floodplain.
Providence
case study
Research in Providence identified
approximately 300 "consequence thresholds" resulting from impacts to about
100 assets across the 45 critical
infrastructure facilities in the floodplain.
Naval Station
Newport
case study
Our latest case study focuses on "a
hazard resilient future for Naval Station
Newport within its coastal community: 
Military installation resilience review
for short-term preparedness and
long-term planning."
Wastewater Treatment
Facilities
case study
In this case, a customized planning tool was developed to help the Rhode Island
Department of Emergency
Management (RI DEM) plan for
the 19 major wastewater treatment
facilities that it regulates.
Westerly
case study
Research in Westerly identified more than 100
"consequence thresholds" resulting from impacts to
11 critical infrastructure
facilities in the floodplain.
Providence
case study
Research in Providence identified approximately 300 "consequence thresholds" resulting from impacts
to about 100 assets
across the 45 critical
infrastructure facilities in the floodplain.
Naval Station
Newport
case study
Our latest case study focuses on "a hazard resilient future for Naval Station Newport
within its coastal community: Military
installation resilience review for short-term preparedness and long-term planning."
Wastewater Treatment
Facilities
case study
In this case, a customized planning tool was developed
to help the Rhode Island
Department of
Emergency Management (RI DEM) plan for
the 19 major wastewater treatment facilities that it regulates.